Mechanical Engineering Co-op | Instron | Jan - Jun 2025
Instron Co-op
6 month co-op working with the R&D team on future products

Instron Frame and Hydraulic Pump
Skills Applied
SolidWorks & PDM
SolidWorks Drawings
Design for Manufacturing (DFM)
Design for Assembly (DFA)
Tolerancing/GD&T
Validation & Verification
Agile
3D Printing
Role & Company
R&D Mechanical Engineering Co-op
Instron builds the load frames and testing systems that manufacturers, universities, and labs around the world rely on to characterize how materials behave under load. I spent six months on the R&D team working on designing and develop products that will be sold to customers.
Instron Logo
Belt Tensioning Subassembly
Drive Pulley Subassembly
Outer Housing
Project One
Redesigning Internal Parts for DFM/DFA
For my first project I was a part of at Instron, I worked on redesigning internal subassemblies/parts of a client facing product that was requiring touch-ups. Stated below were changes that I made:
Belt Tensioning Subassembly:
Changed shafts to have D profile for set screw locking
Redesigned bearing blocks to have an additional tensioning technique so disassembly wasn't required
Drive Pulley Subassembly:
Swapped bevel gear set screws to regular to achieve required torque
Adjusted block to incorporate two pin alignment
Inner/Outer Housing:
Made design tweaks to conform to subassembly changes while making sure it was still manufacturable
Project Two
Installation Drawings for Customers
My second project introduced me to the intricacies of SolidWorks drawings and display states/configurations. I was tasked with creating the installation drawings for a hydraulic pump. This included how tubes were connected, how grips were set up, and how everything, including electrical connections, were connected to the Instron frame (legacy or new).
In the end, I created a total of 8 installation sheets that went through a thorough design review and were prepared to be sent to customers.
Instron Installation Drawing
Instron Installation Drawing

Counterweight Assembly
Carriage Drive Subassembly
Tube Mount


Top and Bottom Limit Stops
Project Three
Counterweight Subsystem Redesign
For my third project that lasted till the end of my co-op, I was assigned with redesigning a counterweight subsystem for a new version of an existing product. The counterweight was connected to a wire that was wrapped around two pulleys and attached to the component (known as the carriage) it was balancing. One of those pulleys was connected to a carriage drive assembly. Below are the changes that were made for each component of the assembly:
Counterweight: Brass moving the balanced component
Previously, wire was routed through counterweight and around two pulleys; changed to mount the wire just at the top of the counterweight
Carriage Drive Subassembly: Assembly driving the counterweight
Went from two machined blocks, both needing alignment, to only one
Simplified sheet metal piece to not need a bend
Changed motor to simplify the BOM
Tube & Mount: Designed to guide counterweight
Redesigned tube to have less machining operations
Designed mount that could handle the two positions it needed with one machined part
Limit Stops: Carriage travel restrictors
Made adjustments to previous limit stops to account for the longer travel of the carriage
Used sheet metal bending to fit around space constraints
Results & Outcomes